CompTIA Project+ (PK0-004) — Question 89

A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Business continuity plan, as it provides strategies for maintaining essential functions during disruptions. The other options, such as the Incident response plan and Regression plan, focus on specific incidents or testing processes rather than overall business operations during critical changes.