CompTIA Project+ (PK0-004) — Question 87
A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.
Which of the following should the project manager do to resolve this issue?
Answer options
- A. Update the scope management plan.
- B. Modify the project baselines.
- C. Implement change control management.
- D. Inform the stakeholders of the issue.
Correct answer: C
Explanation
The correct answer is C, as implementing change control management ensures that all changes to project requirements are formally documented and approved, preventing issues that arise from informal communications. Options A and B do not directly address the issue of undocumented requirements, while D only informs stakeholders without resolving the underlying problem.