CompTIA Project+ (PK0-004) — Question 78
A company engaged a third-party audit firm to provide regular financial oversight for regulatory compliance and requested a project manager to work with the firm.
The PMO declines to assign a project manager and refers to another department within the company. Which of the following is MOST likely the reason for this?
Answer options
- A. There are not enough project managers available for additional work
- B. The work does not align with the strategic objectives of the organization
- C. This is ongoing work the vendor has been hired to perform
- D. The third party has a reputation for expertise in this area
Correct answer: D
Explanation
The reason the PMO did not assign a project manager is likely because the third-party vendor is recognized for its proficiency in financial oversight, making the need for a project manager less critical. Options A and B suggest resource limitations or misalignment with strategic goals, which are not the primary factors here. Option C implies the work is already being managed by the vendor, but the emphasis on their expertise is the key reason.