CompTIA Project+ (PK0-004) — Question 76
During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:
Answer options
- A. risk identification
- B. risk prioritization
- C. risk qualification
- D. risk quantification
Correct answer: D
Explanation
The correct answer is D, risk quantification, as it specifically refers to determining the numerical probability of a risk occurring. Options A, B, and C refer to different processes: risk identification involves recognizing risks, risk prioritization is about ranking risks based on their impact, and risk qualification assesses the nature of the risks without assigning probabilities.