CompTIA Project+ (PK0-004) — Question 73

A PM is asked to keep the Chief Information Officer (CIO) informed of a project's health at a high level on a daily basis. Which of the following is the BEST way for the PM to provide this information?

Answer options

Correct answer: D

Explanation

Using email is the most effective way to provide daily updates to the CIO, as it allows for quick and direct communication. Status reports, meeting minutes, and dashboards may not offer the timely and concise information needed for daily high-level updates.