CompTIA Project+ (PK0-004) — Question 6

A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?

Answer options

Correct answer: C

Explanation

The correct answer is C, Project statement of work, because this document outlines the project's objectives, scope, and deliverables, which are essential to define before moving forward. The project charter (A) is created later to formally authorize the project, while the project management plan (B) and project schedule (D) are developed after the statement of work is established.