CompTIA Project+ (PK0-004) — Question 577
A recent change request was implemented with approval; however, it had an unforeseen negative impact on the critical path. Which of the following measures should be taken to ensure the project is not delayed?
Answer options
- A. Evaluate the impact of the change.
- B. Execute the regression plan.
- C. Identify and document the root cause of the issue.
- D. Validate the change was quality checked.
Correct answer: B
Explanation
Executing the regression plan is essential to revert any unintended effects caused by the change, thus preventing project delays. Evaluating the impact, identifying root causes, and validating quality checks are important but do not directly address immediate corrective actions required to mitigate delays.