CompTIA Project+ (PK0-004) — Question 574
To facilitate product testing, an outside vendor was contracted to provide resources for project completion. Each resource will be given network and door access.
The outside vendor has provided background checks for all the resources. Which of the following should the project manager request from the outside vendor prior to providing access rights for these resources?
Answer options
- A. NDA
- B. LOI
- C. SOW
- D. SLA
Correct answer: A
Explanation
The project manager should request a Non-Disclosure Agreement (NDA) to ensure confidentiality and protect sensitive information. An NDA is crucial before granting access rights to external individuals, while a Letter of Intent (LOI), Statement of Work (SOW), and Service Level Agreement (SLA) do not specifically address the need for confidentiality in this context.