CompTIA Project+ (PK0-004) — Question 56
A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations.
The project team must ensure completion of the:
Answer options
- A. business continuity plan.
- B. incident response plan.
- C. disaster recovery plan.
- D. risk management plan.
- E. quality management plan.
Correct answer: D
Explanation
The correct answer is D, the risk management plan, as it is essential to identify and mitigate risks that could impact the project timeline. The other options, while important, do not directly address the need to manage risks associated with meeting project deadlines and milestones.