CompTIA Project+ (PK0-004) — Question 558

Which of the following would MOST likely trigger a business continuity response?

Answer options

Correct answer: D

Explanation

The correct answer is D because interruptions in electrical services at the primary datacenter directly affect operations and availability, necessitating a business continuity response. Options A and B, while serious, typically involve contractual or project management issues rather than immediate operational crises. Option C is a security concern but does not inherently disrupt business operations like a power outage would.