CompTIA Project+ (PK0-004) — Question 558
Which of the following would MOST likely trigger a business continuity response?
Answer options
- A. If the metrics within an SLA are not met, resulting in penalty payments to a customer
- B. If a project milestone that is critical to delivering a new product on time is not achieved as scheduled
- C. If unauthorized personnel receive confidential communications
- D. If electrical services are interrupted at the primary datacenter
Correct answer: D
Explanation
The correct answer is D because interruptions in electrical services at the primary datacenter directly affect operations and availability, necessitating a business continuity response. Options A and B, while serious, typically involve contractual or project management issues rather than immediate operational crises. Option C is a security concern but does not inherently disrupt business operations like a power outage would.