CompTIA Project+ (PK0-004) — Question 547
A project manager detects a defect in a project deliverable and suspects a team member missed a step during production.
Which of the following tools would be BEST for the project manager to use to confirm this suspicion?
Answer options
- A. Pareto chart
- B. Process diagram
- C. Run chart
- D. Fishbone diagram
Correct answer: D
Explanation
The Fishbone diagram is the most suitable tool for identifying potential causes of defects, allowing the project manager to investigate and confirm if a missed step contributed to the issue. The other options, while useful in different contexts, do not focus specifically on identifying root causes of problems like the Fishbone diagram does.