When a risk event occurs, which of the following documents is BEST suited for recording and tracking new items corresponding to the risk?
Answer options
- A. Issue log
- B. Risk management plan
- C. Communications plan
- D. Risk register
- E. Status report
Correct answer: A
Explanation
The Issue log is specifically designed to track issues that arise during a project, including those related to risk events. The other options, such as the Risk management plan and Risk register, are focused on planning and identifying risks rather than tracking issues that have already occurred.