CompTIA Project+ (PK0-004) — Question 516
A project team is meeting to develop the lessons learned document for archival purposes. In which of the following phases is this project?
Answer options
- A. Closing
- B. Planning
- C. Development
- D. Testing
Correct answer: A
Explanation
The correct answer is A, Closing, because the lessons learned document is typically created at this stage to capture insights for future projects. The other phases—Planning, Development, and Testing—do not focus on documenting lessons learned as they are more concerned with project execution and management.