CompTIA Project+ (PK0-004) — Question 508

A customer approaches a team member to report that old functionality is no longer valid due to technology restrictions. The team member has also noticed this during the execution of the project. The team member agrees with the new functionality provided by the customer, implements the change, and notifies the project manager.
Which of the following actions should the project manager take NEXT?

Answer options

Correct answer: C

Explanation

The correct action for the project manager is to proceed to the next task in the project schedule, as the change has already been implemented and communicated. Updating the project management plan or conducting an impact analysis may not be necessary at this stage, as the change aligns with project objectives and does not require further adjustments.