CompTIA Project+ (PK0-004) — Question 500

When an action is taken on a risk, which of the following is being done and which document needs to be updated?

Answer options

Correct answer: A

Explanation

The correct answer is A because when a risk is mitigated, it is essential to update the risk register to reflect the action taken. Options B and C are incorrect as they refer to different risk responses that do not involve mitigation, and D is incorrect because exploiting risk does not involve updating the risk register in the same context.