CompTIA Project+ (PK0-004) — Question 500
When an action is taken on a risk, which of the following is being done and which document needs to be updated?
Answer options
- A. Mitigating risk, and the risk register should be updated
- B. Accepting risk, and the risk review document should be updated
- C. Avoiding risk, and the risk review document should be updated
- D. Exploiting risk, and the risk register should be updated.
Correct answer: A
Explanation
The correct answer is A because when a risk is mitigated, it is essential to update the risk register to reflect the action taken. Options B and C are incorrect as they refer to different risk responses that do not involve mitigation, and D is incorrect because exploiting risk does not involve updating the risk register in the same context.