CompTIA Project+ (PK0-004) — Question 497

During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure. Which of the following documents should be updated?

Answer options

Correct answer: A

Explanation

The correct answer is A, Incident response, because the changes in business processes directly affect how incidents are managed. The other options, while important, do not specifically pertain to the immediate changes in response strategies for incidents that may arise from business process alterations.