CompTIA Project+ (PK0-004) — Question 494
Which of the following is the MOST likely trigger to update the project risk register?
Answer options
- A. An issue occurs.
- B. A quality audit is passed.
- C. A project milestone is completed.
- D. A stakeholder initiates a change request.
Correct answer: A
Explanation
The correct answer is A because when an issue arises, it can introduce new risks or alter the impact of existing risks, necessitating an update to the risk register. The other options, while significant events, do not directly relate to the identification or reassessment of project risks.