CompTIA Project+ (PK0-004) — Question 48
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
Answer options
- A. Cost baseline
- B. Burn rate
- C. Cost variance report
- D. Total project cost
Correct answer: A
Explanation
The correct answer is A, Cost baseline, as it encompasses the total planned costs for the project, including capital expenditures and anticipated resource costs. Options B and C focus on specific financial metrics related to project spending over time rather than a comprehensive summary of costs, while D, Total project cost, is not as specific as the cost baseline which details the planned expenditure.