The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?

Answer options

Correct answer: A

Explanation

The correct answer is A, Cost baseline, as it encompasses the total planned costs for the project, including capital expenditures and anticipated resource costs. Options B and C focus on specific financial metrics related to project spending over time rather than a comprehensive summary of costs, while D, Total project cost, is not as specific as the cost baseline which details the planned expenditure.