CompTIA Project+ (PK0-004) — Question 474

The project manager of a global project constantly receives complaints from individuals at another location that some team members are not available after lunch on Fridays. This is acceptable to the project manager. Which of the following factors is the MOST likely cause for this scenario?

Answer options

Correct answer: D

Explanation

The most likely cause of the issue is the time zone, as it can lead to differences in working hours across locations. Other options like personal preference, intra-organizational differences, and culture may influence work habits but do not directly account for unavailability due to differing time zones.