CompTIA Project+ (PK0-004) — Question 467
A new project has started, and the project schedule is being built. After the WBS is complete, scheduling of the activities begins. Which of the following is the most likely NEXT step?
Answer options
- A. Sequence the activities.
- B. Allocate the resources.
- C. Set the baseline.
- D. Determine the tasks.
Correct answer: A
Explanation
The correct answer is A, as sequencing the activities is the natural next step after completing the Work Breakdown Structure (WBS). Allocating resources, setting the baseline, and determining tasks are important but come after the activities have been sequenced.