CompTIA Project+ (PK0-004) — Question 459

A project manager is leading an effort to build a new factory near a river, and the local population is concerned about the impact of the factory on the waterway. In response, the local council will conduct regular inspections. Which of the following are the MOST likely effects to the project? (Choose three.)

Answer options

Correct answer: C, F, G

Explanation

The correct answers, C, F, and G, indicate that the project timeline will be affected due to inspections, costs will increase due to the need for compliance and additional resources, and the overall budget will expand to accommodate these changes. Options A, B, D, and E are less likely because the project scope is typically defined by initial requirements, and while additional resources might be needed, it is not one of the top three effects identified.