CompTIA Project+ (PK0-004) — Question 457
A stakeholder has identified a new requirement that enhances the performance of the final deliverable. The project team has evaluated the impact, and it was approved by the CCB. Which of the following actions should the project manager take NEXT?
Answer options
- A. Document the change.
- B. Communicate to the stakeholder.
- C. Implement the change.
- D. Validate the change.
Correct answer: D
Explanation
The correct action is to validate the change to ensure that it meets the necessary requirements and aligns with the project's goals. Documenting the change and communicating with the stakeholder are important but should follow after validation. Implementing the change without proper validation could lead to unforeseen issues in the project.