CompTIA Project+ (PK0-004) — Question 447
An active project has a CPI of 0.92. Which of the following can be determined?
Answer options
- A. The project is currently over budget.
- B. The project has a budget surplus.
- C. The project is ahead of schedule.
- D. The project is behind schedule.
Correct answer: A
Explanation
A CPI of less than 1 indicates that the project is spending more than planned, which means it is currently over budget. The other options are incorrect as they suggest either a budget surplus or being ahead of schedule, which contradict the implication of a CPI lower than 1.