CompTIA Project+ (PK0-004) — Question 447

An active project has a CPI of 0.92. Which of the following can be determined?

Answer options

Correct answer: A

Explanation

A CPI of less than 1 indicates that the project is spending more than planned, which means it is currently over budget. The other options are incorrect as they suggest either a budget surplus or being ahead of schedule, which contradict the implication of a CPI lower than 1.