During the storming stage of a project team's development, it is common to experience confusion about tasks and responsibilities because:
Answer options
- A. there is unfamiliarity with the project structure.
- B. there is a lack of trust among team members.
- C. there are minimal team decisions.
- D. there is no engagement of the team by the project manager.
Correct answer: B
Explanation
The correct answer is B because a lack of trust among team members often leads to misunderstandings and conflicts about roles and responsibilities. While unfamiliarity with the project structure (A) can contribute to confusion, it is trust issues that primarily drive the storming phase's challenges. Options C and D do not directly address the core issue of trust, which is critical during this stage.