CompTIA Project+ (PK0-004) — Question 436
A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would
BEST communicate the need for a WBS to the other managers? (Choose two.)
Answer options
- A. Using the WBS will help prevent work from slipping or being forgotten.
- B. TheWBS will be required on very large projects.
- C. TheWBS will be required if the project manager has the time available to complete it.
- D. TheWBS will aid in determining which resources are required for the project.
- E. The WBS is the best way to determine risks of the project.
Correct answer: A, D
Explanation
Option A is correct because it highlights how a WBS can help manage tasks effectively, preventing oversights. Option D is also correct as it emphasizes the resource allocation benefits of a WBS. Options B and C do not communicate the immediate advantages of a WBS, while option E focuses on risk assessment rather than the task management benefits that are crucial for gaining support from other managers.