CompTIA Project+ (PK0-004) — Question 432

Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?

Answer options

Correct answer: B

Explanation

The Sprint planning meeting is specifically designed to select and prioritize the backlog items that the team will work on in the upcoming sprint. In contrast, the SCRUM retrospective focuses on reviewing the previous sprint, the Daily standup is for daily progress updates, and the Review meeting is about demonstrating completed work rather than planning future tasks.