CompTIA Project+ (PK0-004) — Question 419
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
Answer options
- A. Project schedule
- B. Cost plan
- C. Scope statement
- D. Impact assessment
Correct answer: A
Explanation
The correct answer is A, as the project schedule typically includes detailed information about the resources assigned to each task. The cost plan (B) focuses on budgeting, the scope statement (C) outlines project deliverables, and the impact assessment (D) evaluates potential effects, none of which specifically list resource assignments.