CompTIA Project+ (PK0-004) — Question 4

A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)

Answer options

Correct answer: A, D

Explanation

The Status report provides a current overview of the project's progress, which is essential for keeping stakeholders informed. Meeting minutes document discussions and decisions made during meetings, ensuring that all stakeholders are aware of any changes or updates. The other options, while useful in their own contexts, do not specifically address the need for notifying stakeholders about project status changes.