CompTIA Project+ (PK0-004) — Question 397

A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?

Answer options

Correct answer: A

Explanation

The best approach is to conduct a face-to-face or telephone meeting with the team member, as this allows for immediate clarification and discussion of quality concerns. Sending an email may lack the necessary interaction, while a project team meeting could dilute the focus on the specific issue. Posting on a wiki page may not elicit timely feedback or address the problem directly.