CompTIA Project+ (PK0-004) — Question 397
A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?
Answer options
- A. Conduct a face-to-face or telephone meeting with the team member.
- B. Send an email outlining the concerns to the team member.
- C. Send a project team meeting to obtain feedback from everyone.
- D. Post the issue on the wiki page for input from stakeholders.
Correct answer: A
Explanation
The best approach is to conduct a face-to-face or telephone meeting with the team member, as this allows for immediate clarification and discussion of quality concerns. Sending an email may lack the necessary interaction, while a project team meeting could dilute the focus on the specific issue. Posting on a wiki page may not elicit timely feedback or address the problem directly.