CompTIA Project+ (PK0-004) — Question 387

Which of the following actions by the project team increases the chance of scope creep?

Answer options

Correct answer: B

Explanation

Answer B is correct because strictly following the project plan while incorporating approved changes can lead to additional modifications that may not be fully controlled, resulting in scope creep. The other options, such as informing customers to submit change requests (A) and using a baselined network diagram (C), help manage scope effectively, while following senior management directives (D) may lead to misinterpretations of project scope.