CompTIA Project+ (PK0-004) — Question 38
A project manager is mapping qualifications and available personnel to the project requirements. Which of the following activities is the project manager completing?
Answer options
- A. Team Building
- B. Team Selection
- C. Resource loading
- D. Resource leveling
Correct answer: B
Explanation
The correct answer is B, Team Selection, as it involves choosing the right personnel based on their qualifications for the project's requirements. Team Building (A) focuses on developing relationships within the team, Resource loading (C) pertains to assigning resources to tasks, and Resource leveling (D) is about balancing resource allocation to avoid over-usage.