CompTIA Project+ (PK0-004) — Question 353
A quality control team identified multiple defects in a work product. The team’s analysis traced the defects to the on-site junior-level engineer. For the project manager to get to the root cause, which of the following meeting types should the manager conduct?
Answer options
- A. Stand-up
- B. Retrospective
- C. Kickoff
- D. Face-to-face
Correct answer: B
Explanation
A Retrospective is designed to reflect on what went well and what could be improved, making it ideal for identifying root causes of defects. Stand-up meetings are typically for quick updates, Kickoff meetings are for project initiation, and Face-to-face meetings can be too general without a specific focus on analysis.