CompTIA Project+ (PK0-004) — Question 350
Which of the following is MOST important to the success of a project’s risk management effort?
Answer options
- A. Determine the probability.
- B. Prioritize based on impact.
- C. Maintain an issue log.
- D. Document roles and responsibilities.
- E. Identify the timeline.
Correct answer: B
Explanation
Prioritizing based on impact is essential because it allows project teams to focus their resources on the most significant risks that could affect the project's success. While determining probabilities, maintaining an issue log, documenting roles, and identifying timelines are important aspects of risk management, they do not directly influence the prioritization of risks, which is key to effective risk mitigation.