During the planning phase, a project team identifies a risk that could occur during the closing phase. While performing closing activities, the risk response is triggered. Which of the following documents need to be updated? (Choose three.)
Answer options
- A. Status report
- B. Communication plan
- C. Risk register
- D. Service level agreement
- E. Issue log
- F. Project charter
- G. Scope statement
Correct answer: B, C, E
Explanation
The correct answers are B, C, and E because the Communication plan needs to reflect any updates in stakeholder communication, the Risk register must document the triggered risk response, and the Issue log should include any new issues identified. The other options do not require updates based on the triggered risk response.