CompTIA Project+ (PK0-004) — Question 327
A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates.
This is an example of:
Answer options
- A. outsourcing.
- B. low-quality resources.
- C. benched candidates.
- D. resource planning.
Correct answer: B
Explanation
The correct answer is B, as it indicates that the team is unable to find suitable resources to fulfill project needs. Outsourcing (A) refers to hiring external resources, while benched candidates (C) are those not currently assigned to a project but available. Resource planning (D) is about organizing resources effectively, not about the quality or availability of candidates.