CompTIA Project+ (PK0-004) — Question 324
A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue?
Answer options
- A. Timeline
- B. Quality
- C. Budget
- D. Scope
Correct answer: A
Explanation
The timeline is likely to be most affected since the crash of the authentication server will delay access for employees, thereby pushing back project deadlines. While quality, budget, and scope may also be influenced, the immediate impact on employee access directly correlates with the project's timeline.