CompTIA Project+ (PK0-004) — Question 304
Which of the following is included in a scope document?
Answer options
- A. Individual task cost
- B. Expense worksheet
- C. Estimated budget
- D. Cost comparison
Correct answer: A
Explanation
The correct answer is A, as a scope document details the costs associated with individual tasks within a project. Options B, C, and D may be related to financial planning but are not standard inclusions in a scope document.