CompTIA Project+ (PK0-004) — Question 292
Stakeholders often do not understand the hierarchy of roles and responsibilities on a project team. Which of the following could provide a visual representation?
Answer options
- A. Work breakdown structure
- B. Milestone list
- C. Organizational chart
- D. Action items
Correct answer: A
Explanation
The Work breakdown structure (WBS) is designed to break down a project into manageable sections, clearly outlining the hierarchy of tasks and responsibilities. In contrast, a Milestone list focuses on key project dates, an Organizational chart represents overall company structure without specific project details, and Action items are tasks to be completed rather than a depiction of roles.