CompTIA Project+ (PK0-004) — Question 290

Which of the following is captured when baselining a project?

Answer options

Correct answer: A

Explanation

The correct answer is A, KPI, as Key Performance Indicators are essential metrics that are established when baselining a project to assess its performance. The other options, SV (Schedule Variance), BAC (Budget at Completion), and AC (Actual Cost), are important metrics but are not specifically captured as part of the initial baseline measurement.