CompTIA Project+ (PK0-004) — Question 29
Which of the following techniques modifies the schedule based upon resource constraints?
Answer options
- A. Critical Chain Method
- B. Critical Path Method
- C. Arrow Diagramming Method
- D. Precedence Diagramming Method
Correct answer: A
Explanation
The Critical Chain Method is specifically designed to address resource constraints by modifying the project schedule, making it more flexible. The Critical Path Method focuses on the sequence of tasks and their duration without specifically accounting for resource limitations. The Arrow Diagramming Method and Precedence Diagramming Method are both techniques for visualizing project tasks but do not inherently adjust for resource constraints.