CompTIA Project+ (PK0-004) — Question 265

A customer-requested project change has been approved, implemented, and validated.
Which of the following should the project manager do NEXT?

Answer options

Correct answer: D

Explanation

The correct answer is D, as the project management plan needs to be updated to reflect the changes made to the project. Options A, B, and C are incorrect because the project charter and statement of work pertain to initial project definitions, and lessons learned are documented for future reference, not as a direct response to changes.