CompTIA Project+ (PK0-004) — Question 265
A customer-requested project change has been approved, implemented, and validated.
Which of the following should the project manager do NEXT?
Answer options
- A. Update the project charter.
- B. Update the statement of work.
- C. Update the lessons learned.
- D. Update the project management plan.
Correct answer: D
Explanation
The correct answer is D, as the project management plan needs to be updated to reflect the changes made to the project. Options A, B, and C are incorrect because the project charter and statement of work pertain to initial project definitions, and lessons learned are documented for future reference, not as a direct response to changes.