CompTIA Project+ (PK0-004) — Question 248
Which of the following tools would a project manager use to determine the root cause of an issue?
Answer options
- A. Pareto Chart
- B. Ishikawa Diagram
- C. Histogram
- D. Monte Carlo Analysis
Correct answer: B
Explanation
The Ishikawa Diagram, also known as the fishbone diagram, is specifically designed to identify the root causes of issues, making it the correct choice. In contrast, a Pareto Chart focuses on prioritizing problems based on their impact, a Histogram presents data distribution, and Monte Carlo Analysis is used for risk assessment, not root cause analysis.