CompTIA Project+ (PK0-004) — Question 234

Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer.
Which of the following is the MOST likely impact to Project B?

Answer options

Correct answer: B

Explanation

The correct answer is B because if the changes in Project A occur within the allocated buffer, they should not affect Project B. Options A, C, and D suggest that there will be additional costs, scope adjustments, or schedule changes, which are not necessary if the buffer adequately accommodates the rework.