CompTIA Project+ (PK0-004) — Question 232

A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time.
Which of the following is the BEST option for the project to complete on time and within parameters?

Answer options

Correct answer: A

Explanation

Reducing the project scope is the best option because it directly addresses the issue of exceeding the defect rate while still allowing for timely delivery. Crashing the schedule or applying new resources may not effectively manage the defect rate and could lead to quality issues. Requesting additional budget does not guarantee a solution to the defect rate problem and may not align with the customer's insistence on timely delivery.