CompTIA Project+ (PK0-004) — Question 212

Which of the following activities is MOST likely to be completed in the closing project phase?

Answer options

Correct answer: A

Explanation

Operational training is crucial in the closing phase as it ensures that end-users are prepared to utilize the project deliverables effectively. Testing deliverables and updating the scope statement are typically done in earlier phases, while performing a final quality check is often part of the monitoring phase rather than closure.