CompTIA Project+ (PK0-004) — Question 212
Which of the following activities is MOST likely to be completed in the closing project phase?
Answer options
- A. Operational training
- B. Testing deliverables
- C. Updating the scope statement
- D. Performing a final quality check
Correct answer: A
Explanation
Operational training is crucial in the closing phase as it ensures that end-users are prepared to utilize the project deliverables effectively. Testing deliverables and updating the scope statement are typically done in earlier phases, while performing a final quality check is often part of the monitoring phase rather than closure.