A project manager is implementing a new edition of a magazine with an end-of-the-week deadline. The design analyst notices two main articles were not included, as requested by the client. Which of the following constraints should be considered FIRST?
Answer options
- A. Scope
- B. Quality
- C. Time
- D. Budget
Correct answer: C
Explanation
In project management, time is often the most pressing constraint, especially with a strict deadline like the end of the week. While scope, quality, and budget are important, addressing the time constraint is critical to ensure that the project meets its deadline and includes all necessary articles.