CompTIA Project+ (PK0-004) — Question 198

A project team has just implemented an approved change to a project.
Which of the following should occur NEXT?

Answer options

Correct answer: A

Explanation

The correct next step is to validate the change to ensure that it has been implemented correctly and meets the project requirements. Evaluating the impact of the change is typically done beforehand, while implementing a regression plan and updating the issue log are subsequent steps that might follow validation.