CompTIA Project+ (PK0-004) — Question 192
A project manager receives a call from the area regional building department and is informed that, upon inspection, waterlines from public water access to the project building do not meet local material and installation code specifications. Which of the following items BEST describes the unmet objective?
Answer options
- A. Schedule
- B. Milestone
- C. Gate
- D. Task
Correct answer: D
Explanation
The unmet objective is a 'Task' because it pertains to a specific action that was required to meet compliance with local codes. While 'Schedule', 'Milestone', and 'Gate' refer to broader project management concepts, the failure to meet installation standards directly relates to completing a specific task.