CompTIA Project+ (PK0-004) — Question 189
A functional manager within a project is requesting to edit the display features of an application that is being developed.
Which of the following has the authority to approve the edit?
Answer options
- A. PM
- B. CCB
- C. PMO
- D. SME
Correct answer: A
Explanation
The PM (Project Manager) is responsible for overseeing project changes and has the authority to approve modifications. The CCB (Change Control Board) typically evaluates changes but does not have the final authority. The PMO (Project Management Office) provides support and guidance but does not approve changes directly. SMEs (Subject Matter Experts) can advise but lack the authority to authorize changes.