CompTIA Project+ (PK0-004) — Question 185
A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?
Answer options
- A. Tell the senior manager the estimation is not available yet.
- B. Use the budget from a similar project to generate estimates.
- C. Ask a SME for an opinion and propose an estimate.
- D. Gather the team to immediately generate estimates.
Correct answer: B
Explanation
The correct answer is B because using the budget from a similar project allows for a more informed and realistic estimate based on past experiences. Option A is not proactive, C may not provide the best insights without context, and D could lead to rushed estimates that lack thorough analysis.